Atomenergoproject has accomplished the 2012 Topographic Mapping Program of the Akkuyu NPP area


Atomenergoproject has accomplished the 2012 Topographic Mapping Program of the Akkuyu NPP area

 

Specialists of Atomenergoproject (architect general of Akkuyu NPP) hasve completed field work aimed at topographic mapping of the site of Turkey’s first nuclear power plant.

 

During the field season which started in February the specialists mapped a total area of 735 hectares. The work was carried out in frames of the engineering surveys required for drafting the project documentation. The obtained topographic basis reflects features of natural conditions of the local and state of building structures and engineering utilities.

 

On the site of Akkuyu NPP Atomenergoproject’s specialists continue the technical oversight of the engineering surveys – geological, hydrometeorological and environmental, carried out by Turkish contractors. This field work, which are also necessary for drafting the project documentation, are on schedule and should be completed by the end of November 2012.

 

Reference:

Atomenergoproject OJSC – enterprise of the Rosatom State Corporation, engineering company, general designer of the nuclear power plants.

 

The company developed projects of the majority of NPPs on territory of Russia, Eastern Europe and CIS countries. Atomenergoproject OJSC is a general designer of Busher NPP in Iran, Kudankulam NPP in India, Akkuyu NPP in Turkey.

 

«Atomenergoproject OJSC is a general designer and main contractor of the construction of Novovoronezh NPP-2 (2 power units with VVER-1200 reactors under AES-2006 Project).

 

Press Service Atomenergoproject OJSC